Previous Topic

Next Topic

Book Contents

Book Index

Add a shift or shift series

This section explains the following topics:

Prerequisites

Procedure

  1. Click add_border .

    If a time range has been selected in the calendar before add_border is clicked, this time range is automatically applied.

  2. Select the Add Shift option.

    The Add shift dialog opens. Add Shift Dialog.

  3. Enter data.

    The Shift Type and Shift Start/End fields are validated directly upon input. Once any errors have been corrected, the shift or shift series can be created.
    When entering times for shift start/end that do not correspond to the shift type, a dialog is displayed after saving that refers to the standard time of the shift type and asks for confirmation.
    For possible sources of error, see the Add Shift Dialog.

  4. Click Add.