Defining Rules for Booking Load Units In and Out

The rules for booking load units in and out is defined in the Details tab.

The editing of a track and a storage location is identical. The editing is described below using a track as an example.

Preconditions

Procedure

  1. Select the Material flow > Supermarkets menu.
  2. If necessary, look for the supermarket where the required module is located.
  3. In the row containing the supermarket, click mdm_edit_icon to open the supermarket for editing.
  4. Click the track in the graphical display.

    The track is highlighted in light blue. The Track configuration area appears next to the graphical display.

  5. Select assignment mode:
    Overview: Track/Storage Location Configuration Area
  6. If the Control loop static assignment mode has been selected, select the materials with Material number mdm_edit_icon.

    sm_assignment_mode_kanban_static

    Only the materials whose Kanban control loops have been assigned to the open supermarket are visible.

  7. In the Kanban control loops dialog window, click the required Kanban control loop and assign the material to the track with Assign.

    All materials created in the Nexeed Industrial Application System are visible.

  8. If the Material static assignment mode has been selected, select the materials with Material number mdm_edit_icon.

    sm_assignment_mode_material_static

  9. In the Materials dialog window, click the required material and assign the material to the track with Assign.
  10. Click Saveto accept the changes.

The rules for booking in and out on the track are defined. Depending on the assignment mode selected, the assignment mode or the material number is displayed in the graphical display on the track.