Scheduling order completion

Requirements

Procedure

  1. Open the Order Completion menu.
  2. In the Orders window, in the In Forecast time column, read the completion level of the order (in percent) within the forecast period.
  3. In the Orders window, use drag-and-drop to change the sequence of orders.

    The sequence of orders can only be changed if all orders affected by the change have the same order status. For example, it is not possible to move an order with the status Planned before an order with the status Approved or vice versa.

Order planning is complete.